Civil Engineering : Estimating and Costing - Quiz(MCQ)
The rate of payment is made for 100 cu m (per % cu m) in case of
A)
Rock cutting
B)
Earth work in excavation
C)
Excavation in trenches for foundati
D)
All of the above

Correct Answer :   All of the above


Explanation : * Rock cutting
* Earth work in excavation
* Excavation in trenches for foundation
* Earth work in filling the plinth